TPC were engaged for the design and construction of a new PC3 facility in NSW along with a local builder and experienced trades. The new 125 M2 facility will be used for clinical research and education training and was a small part of a larger fitout on multiple levels in the CBD.

The cleanroom system used for this project was ISO-PHAR due to the flexibility of the system, GMP finishes and chemical resistant wall and ceiling facings which are most suitable for Gaseous decontamination. The lab consisted of numerous fully flush windows looking out over the city along with high visibility through the labs. The doors used were 316# stainless steel doors and frames. Preformed corners were used to provide greater airtightness and greater cleanability.

ISO-PHAR cleanroom system advantages.

  • Timeframe for design development and procurement.
  • Fire rating.  The ISO-PHAR system has the highest cleanroom system fire rating in Australia, along with a very low Smogra rating.
  • Chemical resistant facings.
  • Fully flush design.
  • Multiple service reticulation options.
  • Preformed corners for easy cleanability and airtightness.
  • High durability and aesthetics.

 

PC3 Project nsw FADB0743 PC3 Project nsw HBCM8269 PC3 Project nsw IMG_4419 PC3 Project nsw IMG_4560 PC3 Project nsw IMG_4684 PC3 Project nsw IMG_E4683 PC3 Project nsw IMG_E4692
 

  • Completed:
    Sept 2024
  • BUILDER & CONTRACTOR:
    Total Precision Cleanrooms Aust.

  • LOCATION:
    NSW

 